565 NW Holly Street, Issaquah, WA 98027
(425) 837-7000
 

Apollo Elementary School

Apollo Elementary School Addition/Modernization

Budget: $6.575 million

General contractor
TBD, Tentative Bid Date April 2013

Architect
Cornerstone Architectural Group, 206-682-5000

Features: Currently preparing permit drawings

Keep current: Sign up for Apollo E-News.

Check it out: Follow the progress with photos in the monthly Construction reports.


Updates

  • Febuary, 2014
    • Classroom A/V Systems are starting installation.
    • HVAC units are running and controls are underway.
    • Permanent lighting is complete.
    • Millwork is complete.
    • Sheet metal on roof is nearing completion.
    • Interior and exterior painting is nearly complete.
    • 2nd coat of exterior stucco is browned and nearly complete.
    • Panic hardware is installed and electronic security is underway.
  • January, 2014
    • Roofing is nearly complete.
    • Metal siding, flashing, coping is underway.
    • Stucco work has begun.
    • Window and door installation is nearly complete.
    • Interior is nearing completion (wall covering, cabinets, plumbing, electrical, HVAC).
    • Permanent lighting and HVAC is anticipated to be operational by the end of January.
    • Cafeteria expansion is nearly complete.
    • Interior and exterior painting is nearly complete.
  • October, 2013
    • Framing is nearly complete.
    • Brick exterior will start this week.
    • Painting of original building interior and exterior is nearly complete and prime painting of new classroom walls has begun.
    • Ceiling grid is being installed in classrooms.
    • Sheetrock is nearly complete in classrooms. Multipurpose Room expansion is being sheet rocked.
    • Roofing is continuing due to the extended dry weather.
  • August, 2013
    • Administration area is nearing completion and should be complete by September 3rd.
    • Classrooms 210, 202 and 203 are on schedule to be complete for LRC1 and LRC2 by September 3rd.
    • Concrete slabs are in place and framing of eight new classrooms is underway.
    • Music Room and Library alterations are nearing completion.
    • Cafeteria modifications are underway.
    • Students and Staff will have access to all facilities by September 3rd.
  • May, 2013
    • Project is currently out to bid, bids are due May 29th.
    • Both schools (IVE and AP) are being bid as one project with an Engineers Estimate of 6.5 million dollars.
    • Scope for each school is similar and includes the addition of eight new classrooms, revisions to the Administration area, expansion of the Commons, additions of activity areas and restrooms.
    • Project scope includes construction of a new sand playfield where the existing grass playfield is located, construction of a retention pond and associated storm drain piping, extension of a water line to improve hydrant flow and improve water quality, sidewalks and expansion of parking for staff.
  • March, 2013
    • Elementary addition: Design and construction documents are nearing completion.
    • Elementary addition: King County is reviewing permit drawings.
    • Elementary addition: Capital Projects is coordinating with Principal.
    • Elementary addition: Construction should begin by end of school year.
    • Playfield construction: Work will be under a separate contract (not included in the building addition)
    • Playfield construction: Design and construction documents are nearing completion.
    • Playfield construction: King County is reviewing permit drawings.
    • Playfield construction: Capital Projects is coordinating with Principal.
    • Playfield construction: Construction should begin by end of school year.
  • February, 2013
    • Elementary addition: Design drawings are nearing completion and bid phase drawings underway.
    • Elementary addition: Preliminary set has been submitted to King County and initial comments have been received.
    • Playfield construction: Design drawings are nearing completion and bid phase drawings underway.
    • Playfield construction: Preliminary set has been submitted to King County and initial comments have been received.
  • November, 2012
    • Schematic Design is complete and reviewed by Capital Projects staff and Principal
    • Preapplication meeting with Construction planned for mid-November
    • Anticipate completed bid documents by spring 2013
    • Anticipate Building Permit by summer 2013
    • Anticipate construction start summer 2013 for building additions. Field work will be completed under a separate permit. The site work permit will likely take longer to process due to the usual lengthy storm water review process; our goal is to start the building addition at the same time as Issaquah Valley Elementary School

About this websiteReport a problemThe Issaquah School District provides equal opportunity in its programs, activities, and employment.