Maywood Middle School

Maywood Middle School

Modernization and expansion; Construction started June 2011 following the end of the school year

Budget: $10.5 million

General contractor
M.J. Takasaki, Inc. (206) 324-4448

Architect
Cornerstone Architectural Group, (206) 682-5000

Timeline: Completion August 2012.

Current design drawings and renderings

Features: Modernization and expansion, including addition of two science labs, four classrooms, and expanded core facilities.

Keep current: Sign up for Maywood E-News.

Check it out: Follow the progress with photos in the monthly Construction reports.


Updates

  • May, 2013
    • Project is complete. Work began on the fire alarm system upgrades in mid-May. The mechanical upgrades have been bid and a contractor chosen. Submittal review process on long-lead items is underway.
  • March, 2013
    • Project is complete except for the softball field. The softball field was delayed due to weather and will be completed in the spring/summer.
  • February, 2013
    • Project is complete except for the softball field. The softball field was delayed due to weather and will be completed in the spring/summer.
  • November, 2012.
    • Project is substantially complete and staff has moved in. New softball field is expected to be complete near the end of November.
    • Punch list and commissioning is underway.
  • August, 2012.
    • Two story classroom addition electrical and mechanical trim proceeding nicely. Flooring to begin this week.
    • Cafeteria expansion drywall and wall finishes underway.
    • The west parking lot is being paved this week and striped next week. The rest of the parking areas and bus loop will be completed later in August.
    • Exterior painting, re-roofing of the building proceeding.
    • Main gym flooring and bleachers underway.
    • For a main sewer connection to the Liberty High School Gravity line leading to the City of Renton lift station has been completed. Installation of the new Maywood Middle School vault and pumps will begin soon. The school will continue use of the existing septic field until the City Lift Station becomes operational.
  • June, 2012.
    • Two story classroom addition rough-in electrical, plumbing and HVAC nearing completion. Drywall is underway.
    • Multipurpose room expansion framing nearing completion.
    • Parking lots, bus loops are functional and will be completed over summer 2012.
    • Exterior painting, re-roofing of the building proceeding.
    • Main gym demolition nearing completion.
  • May, 2012.
    • Two story classroom addition rough-in electrical, plumbing and HVAC nearing completion. Drywall underway.
    • Gym expansion has started. Wall has been removed between the original gym and original aux gym. Demo has also started in areas needed to complete the new expanded gym.
    • Landscaping, including irrigation, underway.
    • Parking lots, bus loops are functional and will be completed over summer 2012.
    • Exterior painting, re-roofing of the building proceeding.
  • April, 2012.
    • Two story classroom addition rough-in electrical, plumbing and HVAC nearing completion. Drywall underway.
    • Landscaping, including irrigation, underway
    • Parking lots, bus loops are functional and will be completed over summer 2012.
    • Exterior painting, re-roofing of the building proceeding.
  • March, 2012.
    • Phase 1; new Reception area, Administration area, Counseling offices, Aux gym, Stage expanded library, and new entrance are completed an in use.
    • The courtyard area concrete has been proven and is in use.
    • Parking lots, bus loops are functional and will be completed over summer 2012.
    • Exterior painting, re-roofing of the building proceeding nicely.
    • New classroom addition framing is 75% complete.
  • February, 2012.
    • New aux gym will be ready for use by 2/13/2012.
    • New stage area is substantially complete and construction separation wall has been removed to allow use of the full multipurpose room space. Work on the multipurpose room expansion can begin when the courtyard is ready for use approximately 2/13/2012.
    • New entrance lobby, admin/reception, counseling area and 6th grade wing interior corridor connection for lobby are planned to be ready for use March 1, 2012.
    • District staff and the architect have been concerned about the lack of progress on the new classroom and science lab addition. The contractor was asked for a new project or recovery schedule. M J Takisaki's new schedule shows substantial completion August 2, 2012 which will allow for move-in and setup prior to the start of school. We believe that some of the scheduled activities can be moved up to achieve substantial completion at an earlier date or at least build some float back into the schedule. Staff and the architect will be monitoring the completion schedule, 6 week look ahead schedule, and weekly activities to maintain the pace of the work.
  • August, 2011.
    • Demolition of the existing Administration/Commons and Counseling Offices is complete and reconstruction of the Administration area, new entrance and Counseling offices is underway.
    • Demolition of the parking lots, sidewalks, and courtyard is nearing completion and reconstruction of the new curb, gutter and sidewalks is underway.
    • Shoring of the existing building at the new classroom addition has been completed to allow foundation work to proceed.
    • Grading of new parking lots is underway and ATB paving is planned for 8/17/11.
    • New Admin/Counseling areas have been expanded into the original rotunda; wall-framing nearly complete.
  • June, 2011.
    • The project permit was issued by King County DDES and project is underway.
    • Additional portable classroom placement complete.
    • Contractor mobilization and site investigation are underway.
  • April, 2011.
    • Project still under review with King County DDES.
    • Project bid results received April 14, 2011.
    • Project bids and alternate selection is underway.
    • Additional portable classroom placement underway.
  • March, 2011.
    • Project out to bid mid-March.
    • Start of construction in April with demolition and other significant on-site work starting at the end of school in mid-June.
  • December, 2010.
    • Project still under review with King County DDES
    • Project scheduled to go out to bid in early January 2011 and scheduled to open bids mid February
  • October, 2010.
    • Project under review with King County DDES
  • May, 2010.
    • Implementation of review comments have been received from King County DDES and questions concerning these comments are underway.
    • The hazardous materials survey of the old portable on the site is complete.
  • April, 2010.
    • The first round of permit review comments have been received from King County DDES and implementation of the comments into the permit set of plans is underway.
    • The hazardous materials survey of the old portable on the site to begin the week of April 5th.
    • King County Drainage Review Board is still considering stormwater storage and treatment plan.
  • March, 2010.
    • Permit Pre-Application package has been given to King County DDES.
    • The first round of permit review comments are expected from King County DDES on Thursday March 4th.
    • The process of the demolition of the old portable on the site has begun.
  • November 4. Refinement of spaces still underway with Staff. Architect and Engineer refining building and site plans. Architect to schedule Pre-Application Meeting with King County DDES.
  • October 14. Meetings with Staff, schematic design and budgeting underway.
  • September 22. Preliminary schematic drawings (above) were reviewed with school staff and the Design Committee. The presentation detailed the current status of design, ideas, and proposals. The Design Committee will undertake additional review and provide comments to the Principal and Capital Projects staff.
  • September 9. Schematic design and budgeting are underway.
  • August 3. Schematic design and budgeting are underway.
  • June 30. Met with the building staff prior to the end of the school year. Schematic design underway.
  • June 10. Planning meeting with staff scheduled for Thursday, June 11th.
  • May 20. Discussion of the extension of sewer facilities for this project are underway.
  • May 13. Engineering of the extension of sewer facilities for this project is underway.
  • March 11. Design team is refining original concepts to reflect initial staff input.
  • March 4. School staff is putting together a Planning and Design Committee.
  • February 17. A topographic and boundary survey, which is required by King County DDES for the project, is underway.