Liberty High School

Liberty High School expansion and modernization

Budget (updated June 2011): $19 million

General contractor: Notice of Intent to Award issued to Bayley Construction Company

Architect: Bassetti Architects

Design:

  • Entry (2006 bond projects)
  • Site plan (includes reconfigured classroom wings under possible "phase two" construction*)
  • Schematic (blue section indicates possible "phase two" construction*)

Timeline: Design work continues through summer 2010, when construction on the new science labs began. New science labs were ready for use January 2011. Site preparation, including some demolition and portable placement, will last from summer 2010 through summer 2011, when major construction will begin on the performing arts center. Work is expected to last through summer 2012.

Features: New science labs, new classrooms, new performing arts facility, improved heating and air ventilation, and new roofing.

Keep current: Sign up for Liberty E-News.

Check it out: Follow the progress with photos in the monthly Construction reports.

Submit your comments and ideas: libertybuilds@issaquah.wednet.edu.

Phased construction schedule (updated June 2011): The Liberty design team began its work by outlining a campus master plan, which was built on the question: What is the optimal placement of facilities for long-term use? The result was a two-phased construction schedule. The first phase encompasses 2006 bond projects and a new and expanded performing arts center. Phase two builds on the initial work by reorienting the campus around a new commons area with reconfiguration of the office and counseling areas, addition of an auxiliary gym, and modernizing/daylighting classroom wings. Phase-two work is dependent on a future bond, which could go before voters in February 2012 at the earliest.


Updates

  • August 2014
    • Phase 1
      • Bassetti Architect is finalizing review of the as-builts and Operations and Maintenance Manuals.
    • Phase 2
      • Contractor working on punch list items.
      • Commons floor refinishing is completed on the main area. Gymnasium lower floor will start August 25th.
    • Phase 3
      • New Classroom 5000 Wing
        • Furniture is being placed in the individual classrooms.
        • Staff items are being placed into classrooms.
        • Library shelving is being installed and books are being placed on shelving.
        • Roofing of the main building is completed.
        • Metal wall paneling is 98 % completed.
        • Classroom storefront window frames are installed.
        • Elevator is scheduled for final inspection the week of August 27th.
        • King County Building Final inspection is scheduled for August 25th. Partial King County Fire inspection was completed 8/26. Final inspection is scheduled for 8/28.
        • Masonry work is completed.
        • Mechanical units are being started and readied for commissioning.
        • Fire sprinkler system is completed and ready for inspection August 25th and August 28th.
        • Tack boards, vinyl wall covering and Walltalker located in hallways are approx. 85% completed.
        • All rooms and library have been carpeted. Rubber cove base is complete.
        • All rooms are being cleaned.
        • Electrical trim for lower and upper floor proceeding.
        • Casework is completed in all rooms.
        • Installation of phones and computers has begun.
        • Irrigation work is ongoing.
      • 600 Technology Building
        • Sheetrock is installed and mudding and taping is ongoing.
        • Roofing is completed.
        • Exterior metal siding is approx. 95% complete.
        • Mechanical and electrical rough is approx. 85% complete.
        • Fire sprinkler system is approx. 85% complete.
        • Classrooms 6102 and 6104 are approx. 90% complete and will be ready for use 9/3/14.
      • Science 1000 Wing
        • Audio Visual system and projectors are approx. 95% completed.
        • Electrical and mechanical trim-out is 98% completed.
        • Wainscot in hallways have been installed. Need to install chair rail, tack boards and vinyl wall covering.
        • Ceiling tiles are installed.
        • Rooms are being cleaned and readied for furniture delivery.
        • Hallway walls are painted.
  • June, 2014
    • Phase 1
      • Completed.
      • Bassetti Architect is finalizing the as-builts and Operations and Maintenance Manuals.
    • Phase 2
      • Contractor punch list items complete.
      • Commons floor refinishing is scheduled for the week of July 7th.
    • Phase 3
      • New Classroom Wing
        • Painting is proceeding on both floors and exterior of the 100 Wing.
        • Final roofing of the main building is 90% completed. Final roofing of the 600 wing has begun.
        • Insulated metal wall panels are approx. 90 percent completed. Corrugated metal panels are completed.
        • Classroom storefront window frames are installed.
        • Library curtain window is installed with glazing.
        • Installation of hollow metal door frames is completed.
        • Hollow metal doors are being primed and painted.
        • Elevator is 90% completed.
        • Masonry work is completed.
        • Mechanical units have been installed in the library and 600 Wing penthouses.
        • Ductwork on the lower floor is approx. 95% completed.
        • Classroom HVAC units have been installed.
        • Ductwork on the upper floor is approx. 95% completed.
        • Fire sprinkler lines are approx. 95 percent completed. Fire sprinkler permit submitted in December had not yet been issued by King County.
        • Electrical installation for lower and upper floor proceeding.
        • Casework has begun in the lower south classroom wing.
        • Ceiling grid and fans are being installed in the upper floor north classroom wing.
        • Flooring is scheduled to start the first week of August.
        • Site demolition has begun -removal of old sidewalks and paving underway.
        • Irrigation work has begun
      • 600 Technology Building
        • Sheetrock is installed and mudding and taping is completed.
        • Final roofing is approx. 40% completed.
        • Exterior weather barrier is completed.
        • Classroom storefront window frames installed with glazing.
        • Masonry work nearly complete.
        • Mechanical and electrical rough in has begun
  • May, 2014
    • Phase 1
      • Completed.
      • Bassetti Architect is finalizing the as-builts and Operations and Maintenance Manuals.
    • Phase 2
      • Contractor punch list items complete.
    • Phase 3
      • New Classroom Wing
        • Wood framing on the upper floor is completed.
        • GlueLam beams and wood decking for the library has been sealed.
        • Placement of sheetrock on the lower and upper floors is complete and painting has begun in the north wing. The remaining areas are being taped and mudded.
        • Roofing is approximately 40% complete.
        • Exterior weather protection is completed at the 100 wing and support channels for the metal wall panels are being installed.
        • Classroom storefront window frames are installed and the operable windows are being installed in some areas.
        • Library curtain window is installed with glazing.
        • Installations of hollow metal door frames are approximately 85% completed.
        • Hollow metal doors are being primed and painted.
        • Elevator parts have arrived onsite.
        • Masonry work is approximately 90% completed.
        • Mechanical units have been installed in the library and 600 Wing penthouses.
        • Ductwork on the lower floor is approximately 60% completed.
        • Fire sprinkler lines are approximately 95% completed.
        • Electrical rough-in for lower and upper floor proceeding.
        • Meetings are ongoing with staff on selection of furniture and equipment and preparation for this summer's move. Long lead items ordered.
        • Capital Projects Office and consultants are working with the Liberty HS Science staff and students on the design of the green wall.
        • Window testing was scheduled for the week of May 19, 2014.
      • 600 Technology Building
        • Wood framing is completed.
        • Roofing is approximately 40% completed.
        • Exterior weather barrier is completed around the new construction.
        • Classroom storefront window frames installed with glazing.
        • Masonry work is approximately 80% competed.
        • Old siding has been removed around the perimeter of the old section of the building.
        • Mechanical and electrical rough has begun.
  • April, 2014
    • Phase 1
      • Contractor punch list items complete.
      • Requesting Final Board Approval.
    • Phase 2
      • Contractor punch list items complete.
    • Phase 3
      • New Classroom Wing
        • Wood framing on lower floor is percent complete.
        • GlueLam beams and wood decking for the library is complete.
        • Placement of sheetrock on the lower and main floor is approximate 20% complete.
        • Metal roof decking is complete.
        • Roofing is approximately 40% complete.
        • Exterior weather barrier is complete.
        • Classroom storefront window frames are installed.
        • Window glazing is approximately 10% complete.
        • Mechanical units have been installed in the library and 600 Wing penthouses.
        • Ductwork on the lower floor is approximately 70% complete.
        • Classroom HVAC units are being installed and are approximately 50% complete.
        • Ductwork on the upper floor is approximately 5% complete.
        • Fire sprinkler lines are 95% complete on the lower floor and 85% complete on the upper floor.
        • Electrical rough-in for lower and upper floor proceeding.
        • Meetings are ongoing with staff on selection of furniture and equipment and preparation for this summer's move.
        • Capital Project's Office and consultants are working with the Liberty HS Science staff and students on the design of the green wall.
      • 600 Technology Building
        • Wood framing is approximately 30% complete.
        • Metal roof decking complete.
        • Roofing is approximately 30% complete.
        • Exterior weather barrier is complete.
        • Classroom storefront window frames installed - no glazing.
        • Masonry work is approximately 10% complete.
  • February, 2014
    • Phase 1
      • Contractor work on punch list items.
      • Architect has O&M manuals and As-Builts.
    • Phase 2
      • Administration/Counseling
      • Commissioning for mechanical and electrical system is nearing completion.
      • Contractor working on punch list items
    • Culinary Arts and DECA
    • Monitors to display menus will be installed. Need to complete wiring.
    • Contractor working on punch list items
    • Athletic Area
      • Comissioning for mechanical and electrical systems is nearing completion.
      • Contractor working on punch list items.
      • Commons/Kitchen
      • Monitors to display menus have been installed. Need to complete wiring.
      • S. S. paneling for the kitchen and culinary arts room is being installed.
      • Commissioning for mechanical and electrical system is nearing completion.
      • Contractor working on punch list items.
      • Site
      • Sandblasting of the east and west plazas is complete.
    • Phase 3
    • Project Highlights
      • Steel erection is approximately 95 percent complete for the new classroom building and the 600 wing.
      • Main floor slab on deck has been poured.
      • Mechanical room slab on decks have been poured.
      • Electrical rough for lower floor has begun.
      • In slab electrical work for upper floor is complete.
      • In slab mechanical work for upper floor is complete.
      • Mechanical rough at restrooms is approximately 80% complete at lower and upper floors.
      • Wood framing on lower floor is approximately 95% complete.
      • Wood framing on upper floor is approximately 60% complete.
      • Meetings are ongoing with staff on final selection of furniture and equipment.
      • Capital Projects Office and consultants are working with the Liberty HS Science staff and students on the design of the green wall.
  • January, 2014
    • Phase 1
      • Contractor completing punch list items and the last Change Order.
      • Architect has O&M manuals and As-Builts.
      • Phase 2
      • Administration/Counseling
        • Blinds are installed.
        • Commissioning for mechanical and electrical system is nearing completion.
      • Culinary Arts and DECA
        • Monitors to display menus will be installed within the next couple of weeks.
      • Athletic area
        • Commissioning for mechanical and electrical system is nearing completion.
      • Commons/Kitchen
        • Monitors to display menus will be installed within the next couple of weeks.
        • S S paneling for the kitchen and culinary arts room will be installed the week of January 13th.
        • Commissioning for mechanical and electrical system is nearing completion.
      • Site
        • New ticket booth is complete.
        • Landscaping is approximately 95 percent complete.
        • Irrigation system is approximately 95 percent complete.
        • Sandblasting of the east plaza complete. West plaza scheduled for the week of January 13th.
      • Phase 3
        • Steel erection is approximately 75 percent complete.
        • Metal decking is approximately 45 percent complete.
        • Underground plumbing is complete.
        • Underground electrical is complete.
        • Wood framing is approximately 45 percent complete.
        • Meetings are ongoing with staff on selection of furniture and equipment.
    • October, 2013
      • Phase 1
        • Contractor working on punch list items, as-builds, operations and maintenance manuals.
      • Phase 2
        • Administration/Counseling
          • Spaces are occupied.
          • Blinds are installed.
          • Commissioning for mechanical and electrical system underway.
        • Culinary Arts and DECA
          • Culinary arts room and training is complete.
          • DECA classroom and store are operational.
        • Athletic area
          • Electrical and mechanical are working on final trim.
          • Acoustical ceiling tiles have been installed.
          • Weight room and Training room floors are complete.
          • Misc. electrical trim work still in progress.
          • Commissioning for mechanical and electrical system underway.
        • Commons/Kitchen
          • Kitchen is operational and training has been completed.
          • Commons lights are operational.
          • Acoustical wall panels are complete.
          • Wood paneling is approximately 95 percent complete.
          • Roofing contractor is approximately 90 percent completed with flashing.
        • Site
          • New ticket booth is approx. 795 percent complete
          • Plaza around ticket booth is approx. 890 percent complete
          • Main entry plaza planters are approx. 75 percent complete
      • Phase 3
        • Hazardous material abatement is complete
        • Kassel Construction has completed pouring of footings.
        • Footing drains are being installed.
        • Below grade waterproofing is approximately 30 percent complete.
        • Underground plumbing is complete.
        • Power, data and intercom are operational in the Tech building.
        • Underground electrical is 95 percent complete.
        • Vapor barrier has been installed at all slabs on grade locations.
        • Concrete floor are scheduled to be poured the week of October 21st.
      • Science lab
        • Science room and ASB room are complete and occupied. Wall covering for the ASB room is to arrive the week of October 28th and the new display cabinet will arrive the week of November 4th. Contractor has completed punch list items, excluding the two listed.
    • August, 2013
      • Phase 1
        • Contractor working on punch list items, as-builts, and operations and maintenance manuals.
        • Electrical contractor is working on the repairs to the damaged transformer.
      • Phase 2
        • Administration/Counseling
          • Staff has moved into their new office spaces
        • Culinary Arts and Marketing
          • Tiling is complete in the Culinary Arts room.
          • Kitchen equipment is arriving on site the week of August 12th.
          • Casework has been completed in the marketing classroom.
          • Casework for the student store will be installed.
        • Athletic area
          • Walls are painted and wainscot is being installed in hallways
          • Wood floor installation is in progress
          • Floor prep has begun for new flooring
          • Windows have been installed
          • Metal siding is near completion
          • Mechanical units are installed in the new penthouse
          • Electrical and mechanical are working on final rough in
          • Casework has been completed in the training, fitness and PE offices
          • Display cabinets and benches are being installed in the gym foyer
          • Tiles in the public restrooms are complete.
        • Commons/Kitchen
          • Mechanical units have been installed in the penthouse
          • Walls in the Commons are be prepped for final finishes
          • Waterproofing of exterior walls in near completion
          • Chillers have been installed
          • Windows have been installed
          • Quarry tiles are installed in the kitchen
          • Walk-in cooler and freezer are installed. Need to complete electrical and mechanical.
          • Kitchen equipment is on site and being installed.
        • Site
          • New ticket booth is approx. 70 percent complete
          • Plaza around ticket booth is approx. 85 percent complete
          • Main entry plaza planters are approx. 75 percent complete
      • Phase 3
        • Hazardous material abatement is complete
        • Demolition is in progress, they are approximately 90 percent complete
        • Earthwork contractor is proceeding with installing valves and back flow preventers on the fire and domestic water lines
        • Contractor is pouring new concrete curbs and backfilling for the future staff parking stalls the week of August 12th
      • Science lab
        • New science lab & ASB Classroom inspection complete, drywall to begin.
    • May, 2013
      • Liberty High School Sewer Extension and lift station
        • Briarwood ES and Liberty HS are now tied into the new City of Renton Sewer lift station.
      • Phase 1
        • Contractor working on punch list items, as-builds, and operations and maintenance manuals.
      • Phase 2
        • Administration/Counseling
          • Framing is complete and painting is approx. 85 percent complete.
          • Wall coverings are being installed and are 90 percent complete.
          • Lighting fixtures are installed.
          • Cabinets are installed.
          • Electrical and mechanical are working on final rough in.
        • Athletic area
          • Roofing is complete.
          • Framing of interior walls is complete.
          • Sheetrock is being installed in the aux gym and is approx. 90 percent complete.
          • Sheetrock is being installed in the training and weight rooms.
          • Locker rooms and auxiliary spaces are being primed.
          • Windows are approx. 75 percent complete.
          • Metal siding supports are installed. Siding schedule to start the week of May 20th.
          • Mechanical units are installed in the new penthouse.
          • Electrical and mechanical are working on final rough in.
        • Commons/Kitchen
          • Roofing is approx. 90 percent complete.
          • Mechanical units have been installed in the penthouse.
          • Commons floor concrete slab has been poured.
          • Interior wall framing is approx. 85 percent complete.
          • Exterior CMU walls are complete and being washed.
        • Site
          • New ticket booth is approx. 55 percent complete. CMU walls erected and roof framing complete.
          • Plaza around ticket booth is approx. 85 percent complete.
          • Main entry plaza planters are approx. 75 percent complete.
      • Phase 3
        • Bidding documents are on the street. Bid date is May 21, 2013 at 2:00 PM.
    • March, 2013
      • Liberty High School Sewer Extension and lift station
        • City of Renton has completed work and is waiting for final connection to the lift station
        • Contractor has completed the installation of the force main from the lift station to the point of connection on 138th street. Repaving on 138th Street postponed until dry weather.
      • Phase 1
        • The contractor is working on the punch list items.
        • Flooring is complete.
        • The heating system is operational and in use. Commissioning of the heating system is underway.
      • Phase 2
        • Sheetrock for the administration and counseling areas is complete.
        • Electrical rough-in for the administration and counseling areas is complete.
        • Window frames are in for the administration and counseling areas. Glazing is complete in the counseling areas.
        • Roofing is 90 percent complete for the administration and counseling.
        • HVAC ducts are 90 percent complete in the admin and counseling offices.
        • Fire Sprinkler lines are 90 percent complete in the admin and counseling offices.
        • Earthwork contractor has completed grading for the commons and kitchen area. The plumber and electricians are working on under-slab utilities. Floor slab has been poured in some areas of the commons.
        • Steel erectors have completed the athletic area and they are 45 percent completed with the commons area.
        • Framing for the athletic areas is 75 percent complete.
        • Roofers have started on the athletic wing roof.
        • Electrical and mechanical under slab utilities is completed in the locker area. Electrical and plumbing rough in is 90 percent completed.
      • Phase 3
        • Design is proceeding. Staff from Bassetti Architects and Capital Projects has met with school staff on the use of their individual spaces and their needs.
        • Bid opening planned for late May.
    • February, 2013
      • Liberty High School Sewer Extension and lift station
        • Contractor has completed all testing on the lift station equipment
        • Issaquah School District Capital Projects is working on scheduling the last connections to the lift stations.
      • Phase 1
        • The contractor is working on the punch list items.
        • Flooring is approximately 95 percent complete.
        • Commissioning of the heating system is underway.
        • Training for sound, lighting, drapes, rigging, mechanical and electrical systems are scheduled over the next several weeks.
      • Phase 2
        • Framing for the administration area is complete and sheetrock is approximately 85 percent complete.
        • Electrical rough-in for the administration and counseling areas is 90 percent complete.
        • Under slab plumbing and electrical for the kitchen and "L" Café are complete.
        • Concrete has been placed at the stairs leading to the lower athletic areas, second floor of the athletic area, stairs at the commons entrance.
        • Contractor has started forming footing for the kitchen.
        • The existing ticket booth has been demolished. Grading has started and digging for footings is underway.
        • Structural columns for the second floor to the athletic area are complete. Roof trusses are being placed.
        • Roofing on the administration and counseling areas is approximately 40 percent complete.
        • Air and moisture barrier is being applied to the administration and counseling exterior walls.
      • Phase 3
        • The Architect has submitted construction documents to King County Building Department for permitting.
        • Design is proceeding. Staff from Bassetti Architects and Capital Projects has met with school staff on the use of the individual spaces needs.
    • November, 2012
      • Liberty High School Sewer Extension
        • Work on sewer extension from 162nd Ave along 137th street is proceeding. Contractor should have this portion of the sewer line completed this week. The section of sewer line from 137th to the lift station is complete. This will complete sewer line route installation. The City lift station completion will be February-March 2013.
      • Phase 1
        • Hydroseeding and mulching has been completed at the detention pond.
        • Mechanical contractor has completed installation of air ducts and hydronic loop lines. Start up for the boiler and AHU units is scheduled for the week of November 5th.
        • Painters are approximately 80 percent complete.
        • Casework has been installed in the choral and instrument rooms.
        • Stage rigging is complete. Electricians are pulling wire to the rigging for lights.
        • Erection of the entry window wall is complete. Contractor is installing doors.
        • Ceramic tile is complete in the make-up room restrooms and tiling has started in the main men's and women's restrooms.
        • HVAC and electrical work is approximately 95 percent compete in the black box. The area has been painted and the wood floor is being installed.
        • Roofing and flashing are completed.
        • Lighting in the choral and instrument rooms is installed and operational.
        • The staging scaffolding platform in the theater has been removed.
        • Sheetrock contractor is working on taping and mudding the walls in the theater.
        • Acoustical wall panels are being erected in the theater; they are about 40 percent complete.
      • Phase 2
        • Structural steel erection has started in the administration area. Concrete slab for the administration extension is completed. Concrete masonry units being placed along the south admin wall.
        • Below slab electrical and plumbing in the administration and counseling areas is complete.
        • Below slab electrical and plumbing in the locker rooms and new gym entry hallway is proceeding. They are approximately 60 percent complete.
        • Final connection to the gas meter is complete.
        • Footings for the locker rooms and gym entry hallway are complete.
        • Formwork for the concrete walls is approximately 80 percent complete.
        • Placement of the new CMU wall for the gym entry hallway is approximately 80 percent complete.
      • Phase 3
        • Bassetti Architects and staff from the Capital Projects office have been meeting on a regular basis with LHS staff to review current plans for both Phase 3 and the Stadium.
    • August, 2012
      • Phase 1
        • Earthwork contractor is approximately 90 percent completed on resizing of the existing detention pond. The resized pond will accommodate Phase 3 including stadium work. They are doing final grading of the south parking lot. Light poles are installed. Curbing is proceeding.
        • Mechanical rough in is approximately 50 percent complete. The classroom HVAC units have been placed in the mechanical penthouses. Electrical is approximately 65 percent completed. They are pulling wire in the classrooms and staring rough-in for conduits in the theater fly loft.
        • The concrete floor in the theater is complete and framing of interior walls has started.
        • Electrical contractor is continuing with placement of below slab conduits.
        • Sheetrock is being placed in the south classrooms. They are approximately 20 percent complete.
        • The temporary weight room and locker rooms to be completed August 3rd. Movers are scheduled on site August 6th to move items into these rooms.
        • Placement of structural steel for the entry has not been started.
      • Phase 2
        • Contractor has mobilized onsite and has placed construction fencing around the site. Abatement has started in the locker rooms and will proceed to the commons, theater and administration.
        • Mechanical, Electrical and Fire Sprinkler subcontractors are inspecting the building and have started shutting down necessary system in preparation for the start of demolition.
        • Demolition has begun. The contractors schedule shows major demolition complete before the start of school.
        • Preparation for the Admin area footing is underway.
      • Kitchen, Commons, Library classroom, Copy room and DECA
        • The walls are up in the temporary library classroom, DECA, and the serving kitchen. Cabinets are installed in temporary DECA and copy room. All bookshelves and carpet are removed from the Library-turned-Commons.
    • June, 2012
      • Masons have completed placement of concrete masonry units for the theater.
      • Steel trusses and metal deck for the stage and theater house have been installed. Catwalks for the stage and theater house are installed. Steel erectors are working on installing stairs and hand railing.
      • Roofers have begun laying roofing for the music wing. They are approximately 70 percent complete.
      • Electrical contractor is continuing with placement of below slab conduits.
      • Mechanical has removed the existing boiler in preparation for structural work and new boilers and started to place new air ducts in the music wing.
      • The air and moisture barrier has been applied to the exterior walls of the theater and stage.
      • Interior stud walls for the music wing is approximately 90 percent complete.
      • Contractor has started to place hollow metal door frames in music room area.
    • May, 2012
      • Contractor has completed installation of the underground return ductwork.
      • Mason has completed the erection of the east theater wall. They are approximately 90 percent completed on the north wall.
      • The grading for the tennis court is completed. Asphalt begins on May 21st.
      • Placement of the roof trusses for the theater house will begin the week of May 21st.
      • Steel erectors have completed the installation of the two stairs from the stage to the catwalks.
      • Electricians have completed the installation of the emergency battery backup system.
      • Roofing will begin over the music classroom wing the week of the 21st.
      • The interior partition for the music classrooms is approximately 90 percent completed.
      • Phase 2 walk through for contractors was held on May 14th. At this time, there are five contractors interested in the project.
      • Coordination of Phase 2 move with staff is ongoing.
      • Preparation and coordination of summer work to ready the school for the start of Phase 2 continues. Start of conversion work begins the day after school is out.
      • Sewer work is scheduled to begin June 19th.
    • April, 2012
      • Contractor has completed installation of the underground return ductwork. Area has been backfilled and wall footing poured to allow construction of structural masonry walls.
      • Masons are proceeding with placement of concrete masonry units for the east and north theater walls. They are approx. 75 per completed. The electrical contractor is working in conjunction with the masons placing conduits. Structural Steel erectors have completed placement of the metal roof deck over the music wing and the theater loft. They are working on placement of the steel stairway leading from the stage to the catwalks. Earthwork contractor has completed the removal of asphalt for the future tennis courts. They are approx. 90 percent complete on rough grading this area. General contractor is working on forming the east tennis court retaining wall. They have complete erecting the west tennis court retaining wall.
      • Capital Projects is working closely with the Phase 1 contractor staff and the design team on coordination of work related to Phase 2 as well as sewer line extensions and the City of Renton lift station during the summer.
      • Phase 2 work is scheduled to go out to bid May 7th. We plan to have the Authorization of Notice of Intent to Award on the June 13th Board Meeting Agenda.
    • March, 2012
      • Earthwork contractor is proceeding with excavation work for the tennis court footings. They are also working on placement of catch basins for the new storm water system.
      • Masons are continuing with placing concrete masonry units for the north theater wall and proscenium opening.
      • Electrical is working with the masons with conduit placement. They are also working on the installation of the new transformer and switchboard in the existing and new electrical rooms.
      • Steel erectors are proceeding with placement of steel columns and roof trusses for the music classroom area.
      • General contractor is forming footings and stem walls for the tennis court retaining walls.
      • Below grade waterproofing has started for the music wing.
    • February, 2012
      • Water damage to portions of the underground HVAC ductwork has delayed work in those areas. The contractor has adjusted the areas of work to start masonry wall construction in unaffected areas. While not their preferred sequence of installation, starting the masonry walls in unaffected areas allow repair of the ductwork to occur concurrently with wall construction.
    • January, 2012
      • Contractor has poured the concrete walls for the lower floor orchestra pit. Placement of slab on grade concrete floors has begun.
      • Earthwork contractor is proceeding with excavation for footing for the future Black Box and music rooms. Installation of footing drains around lower floor footing is underway.
      • Electrical has completed rough-in of conduits for the lower floor. They have erected the temporary power shelter and pulled feeders to two existing electrical panels. This will allow removal of the old transformer pad and vault.
      • Mechanical contractor has completed installation of the underground waste lines for the northeast restroom and the sump pump.
      • The fiberglass underground air duct is being installed. Before the full length of duct could be encased in CDF concrete, a dewatering pump failure and subsequent flooding allow the duct to float and partially fill with water. The broken duct will need to be replaced. The contractor is working with their insurance company to correct the work.
    • August, 2011
      • Bids were opened on August 3 for Phase I of the Liberty High School Addition and Modernization project. Four bids were received. An Authorization to issue a Notice of Intent to Award is on the board agenda for August 9, 2011.
      • VECA is on schedule with the installation of the new primary service. Base bid work will be completed on August 5, 2011.
      • PSE is scheduled for final power crossover on August 4th. This will require a full building power shutdown. Staff members were notified in advance. (Power crossover is now complete.)
      • VECA is scheduled to be off-site by August 12.
    • June, 2011
      • Phase 1 work is proceeding to complete bid documents for the new Performing Arts Center, new support facilities and site work, and utility relocation and storm drainage facilities for Phase 1 and Phase 2 work, including stormwater and detention facilities.
    • May, 2011
    • April 2011
      • Bid period to start 4/25/2011.
      • King County Water District 90 has approved the storm drainage and utility plans.
      • King County Building Department is continuing with review of the permit set.
    • March 2011
      • The project is scheduled to start demolition and construction following the end of school in mid-June 2011.
    • January 2011
      • Architect has submitted documents to the King Count Building Department for permit.
      • Owner and Architect coordination meetings are continuing on a weekly basis.
      • Architect is now in the Construction Document phase of the project.
    • December 2010.
      • Science
        • General Contractor is coordinating final inspections for building, fire, plumbing and electrical. This will occur this week.
        • Consultants are scheduled to do punch lists this week.
        • Move in for staff is schedule over winter break
      • Phase 1
        • Architect and consultants are proceeding through design development. Owner is meeting with consultants on a weekly basis.
        • Consultants and Owner meet with the King County Building Department to review the project and discuss any outstanding issues or concerns.
        • Architect is proceeding with the intent to submit for building permit in December.
    • November 2010.
      • Science
        • Casework installation has begun.
        • Electrical rough-in is complete. Electrical trim work is about 40% complete.
        • Mechanical rough-in is complete. Mechanical trim work has not started.
        • Floor prep work has begun. Flooring installation will being the week of November 8th.
      • Phase 1
        • Design Development phase is completed and the design team is moving into the Contract Document phase.
        • The Design Team has been meeting meeting with staff to review their individual areas.
        • The Design Team met with King County for the Mandatory Pre-Application process. The County's comments and concerns will be reviewed by the Team.
        • Next milestone is the submittal for buidling permit in December.
    • October 2010.
      • Science
        • Casework installation has begun.
        • Electrical work is approx. 80 percent completed.
        • Mechanical work is approx. 85% completed.
        • Painting is 95% completed.
      • Phase 1
        • Design Development Phase will be completed this week and Construction Documents will begin next week.
        • Meetings are scheduled the latter part of October with Liberty staff to review of program and space layout.
    • March 2010.
      • Schematic design work continues to develop a site/building master plan. The team continues to review design options to address the current scope of work and long term campus needs. The master plan will address long-term future needs so the current project will not inhibit or limit future options.