Bond Projects

2016 Bond Projects Current Budget Status
Beaver Lake Middle School Upgrade/Update $8,500,000 Planning and/or Design Estimated completion date September 2020
Central Administration Building $7,500,000 Planning and/or Design

Investigation and documentation of existing conditions and as-built conditions have been completed.

Space planning work and finishes and furnishing selections have been completed. King County/Comcast have been working to bring a fiber connection to the building to link the new building into the District network. This should be completed in early-to-mid-July. Maintenance and servicing and repair of existing systems including the fire alarm, security and card access system, building control systems, HVAC and elevators have been completed or are underway. Replacement of caulking at exterior windows is in process. Poor concrete in some sidewalk areas has been replaced. The parking area has been resealed and re-striped following replacement of some paving and crack repairs. 

Tenant improvement documents are nearly complete for submittal to the City for permit approval.

Cougar Ridge Expansion Project $12,000,000 Under Construction On track for Substantial Completion September 5, 2018
Discovery Elementary Expansion/Remodel $9,000,000 Under Construction Tentative Bid Date May 2018; Estimated Completion September 2019
Elementary #16 $36,500,000 Planning and/or Design Estimated completion date of September 2020 dependent on land acquisition.
Elementary #17 $38,000,000 Planning and/or Design Estimated completion date of September 2021 dependent on land acquisition.
Endeavour Expansion/Remodel $9,000,000 Under Construction

Tentative Bid Date May 2018; Estimated Completion September 2019

Maple Hills Expansion/Remodel $7,000,000 Planning and/or Design Estimated completion date September 2020
New High School #4 $120,000,000 Planning and/or Design Estimated completion date of September 2021 dependent on land acquisition.
New Middle School #6 $74,000,000 Planning and/or Design Estimated completion date September 2020
Pine Lake Middle School Rebuild $72,000,000 Under Construction On track for Substantial Completion September 5, 2018
Sunset Expansion Project $9,000,000 Under Construction On track for Substantial Completion September 5, 2018
2012 Bond Projects Current Budget Status
Apollo and Issaquah Valley Expansion Projects $15,350,000 Final Acceptance Project was approved as Final by the Issaquah School District Board of Directors on February 8, 2017.
Clark Elementary School Rebuild $41,000,000 Substantially Complete Project was Substantially Complete on August 16, 2017.
Gibson Ek High School $5,900,000 Substantially Complete Date of Substantial Completion was 8/30/16.
Issaquah Middle School Rebuild $63,500,000 Substantially Complete The building met Substantial Completion on 8/16/2016.
Liberty High School Addition and Modernization Phase II and III $61,620,000 Substantially Complete Phase II work is not Final.  Contractors continue to work on punchlist items. Phase III work approved as Final by the Issaquah School District Board of Directors on December 14, 2016.
Liberty High School Grandstand Project $4,875,000 Final Acceptance Date of Substantial Completion was 8/15/16.  The project was accepted as Final on 9/6/2016.
Middle School Turf Field & Track Improvements $11,000,000 Final Acceptance The projects were approved as Final by the Issaquah School District Board of Directors on January 10, 2018.
Skyline High School Grandstand & Stadium Project $10,800,000 Final Acceptance The Grandstand was accepted as Final on 8/22/16.  Substantial Completion for Stadium was 10/28/2016 and accepted as Final on 8/1/2017.
Sunny Hills Elementary School Rebuild $35,500,000 Final Acceptance The building was approved as Final by the Issaquah School District Board of Directors 9/27/17.
2006 Bond and Levy Projects Current Budget Status
Briarwood Elementary Rebuild $26,285,000 Final Acceptance The project was approved as Final by the Issaquah School District Board of Directors on February 10, 2016.
Creekside Elementary (E15) $23,544,000 Final Acceptance The project was approved as Final by the Issaquah School District Board of Directors on November 9, 2011.
Issaquah High School Reconstruction $96,225,000 Final Acceptance The project was approved as Final by the Issaquah School District Board of Directors November 28, 2012.
Liberty High School Addition and Modernization Phase I $24,850,000 Final Acceptance The project was accepted as Final by the Issaquah School District Board of Directors on April 23, 2014.
Maywood Middle School Addition & Modernization $25,940,000 Final Acceptance Maywood Modernization and Maywood Building/Mechanical Upgrades are Final. The Maywood Classroom Infill Project is Substantially Complete.