Bond Projects

Beaver Lake Middle School Upgrade/Update

Entry Revised
The project will provide cosmetic upgrades, HVAC improvements and updates to the 23 year old Plateau middle school.
Upgrades to Beaver Lake Middle School will update the educational facility and improve the learning environment for over 850 students and staff.
Project Information
Original Project Estimate: $8,500,000
Project Budget: To Be Determined
Budget: To Be Determined
Explanation:
Funding source: 2016 Bond
Project status: Under Construction
Architect: Integrus Architecture
Contractor: To Be Determined
Estimated completion: December 2021

June 2021

  • Work to include; entry area upgrades, HVAC upgrades, additional Music Program storage, Admin Office area reconfiguration, enclosures at exterior stairwells, new flooring in the classrooms and a new covered play area.
  • The project bids were received May 12, 2021, contractor has been chosen and work expected to begin late-June/early-July 2021.
  • Building permit application was submitted to the City of Sammamish in mid-December 2020. First round of review comments received and have been responded to by the design team. Awaiting final round of comments.
  • ISD and the Design Team continue to work with the Principal to refine finishes, prioritize scope, etc.
  • Painting of the exterior complete.
  • Would hope to commence work in Summer 2021 depending upon permit issuance.

May 2021

  • Work to include; entry area upgrades, HVAC upgrades, additional Music Program storage, Admin Office area reconfiguration, enclosures at exterior stairwells, new flooring in the classrooms and a new covered play area.
  • The project bids were received May 12, 2021, contractor has been chosen and work expected to begin late June 2021.
  • Building permit application was submitted to the City of Sammamish in mid-December 2020. First round of review comments received and have been responded to by the design team. Awaiting final round of comments.
  • ISD and the Design Team continue to work with the Principal to refine finishes, prioritize scope, etc.
  • Painting of the exterior complete.
  • Would hope to commence work in Summer 2021 depending upon permit issuance.

April 2021

  • Work expected to include; entry area upgrades, HVAC upgrades, additional Music Program storage, Admin Office area reconfiguration, enclosures at exterior stairwells, new flooring in the classrooms and a new covered play area.
  • Building permit application was submitted to the City of Sammamish in mid-December 2020. First round of review comments received and have been responded to by the Design Team.
  • ISD and the Design Team continue to work with the Principal to refine finishes, prioritize scope, etc.
  • Painting of the exterior complete.
  • Would hope to commence work in Summer 2021 depending upon permit issuance.

March 2021

  • Building permit application was submitted to the City of Sammamish in mid-December 2020. First round of review comments received and being responded to by the design team.
  • ISD and the Design Team continue to work with the Principal to refine finishes, prioritize scope, etc.
  • Work expected to include; entry area upgrades, HVAC upgrades, additional Music Program storage and enclosures at exterior stairwells.
  • Painting of the exterior complete.
  • Would hope to commence work in Summer 2021 depending upon permit issuance.

January 2021

  • Building permit application was submitted to the City of Sammamish in mid-December 2020.
  • ISD and the Design Team continue to work with the Principal on design development and
    program needs.
  • Work expected to include; exterior repaint, entry area upgrades, HVAC upgrades, additional Music Program storage and enclosures at exterior stairwells.
  • Painting of the exterior complete.
  • Would hope to commence work in Fall 2021 depending upon permit issuance.

December 2020

  • ISD and the Design Team continue to work with the Principal on design development and
    program needs.
  • Work expected to include; exterior repaint, entry area upgrades, HVAC upgrades, additional Music Program storage and enclosures at exterior stairwells.
  • Painting of the exterior complete.
  • Building permit application to the City of Sammamish is expected in mid-December 2020.
  • Would hope to commence work in Fall 2021 depending upon permit issuance.

November 2020

  • ISD and the Design Team continue to work with the Principal on design development and program needs.
  • Work expected to include; exterior repaint, entry area upgrades, HVAC upgrades, additional Music Program storage and enclosures at exterior stairwells.
  • Painting of the exterior complete.
  • Building permit application to the City of Sammamish is expected in late-November/early-December 2020.
  • Would hope to commence work in Fall 2021 depending upon permit issuance.

October 2020

  • ISD and the Design Team continue to work with the Principal on design development and program needs.
  • Work expected to include; exterior repaint, entry area upgrades, HVAC upgrades, additional Music Program storage and enclosures at exterior stairwells.
  • Painting of the exterior complete.
  • Pre-Application with City of Sammamish occurred in Mid-August. Expecting to submit to City of Sammamish for permits in late November 2020.

September 2020

  • ISD and the Design Team continue to work with the Principal on design development and program needs.
  • Work expected to include; exterior repaint, entry area upgrades, HVAC upgrades, additional Music Program storage and enclosures at exterior stairwells.
  • Painting of the exterior complete.
  • Pre-Application with City of Sammamish occurred in Mid-August. Expecting to submit to City of Sammamish for permits in late November 2020.

August 2020

  • ISD and the Design Team continue to work with the Principal on design development and program needs.
  • Work expected to include; exterior repaint, entry area upgrades, some HVAC upgrades, additional Music Program storage and enclosures at exterior stairwells.
  • Pre-Application with City of Sammamish occurred in Mid-August.

June 2020

  • ISD and the Design Team continue to work with the Principal on design development and program needs.
  • Work expected to include; exterior repaint, entry area upgrades, some HVAC upgrades, additional Music Program storage and enclosures at exterior stairwells.
  • ISD is working with the Design Team and the Principal on potential color schemes for the exterior of the building. Building exterior to be painted over Summer 2020.
No additional documents are available for this project.